Fiber to the Home
Construction efforts are nearing completion on facilities installation. Crews will be focusing on restoration activities for the next several weeks to get our beautiful city back in tip-top shape after the construction activities.
Project Category | % Complete |
Conduit Installation | 100% |
Cable Placement | 100% |
Splicing | 80% |
Drop Installation | 95% |
Service Activation | 42% |
Video Service
We are continuing testing of service with Yondoo and working with their staff to coordinate installation efforts. I expect they will be launching video service in Sandy in May or June.