Fiber to the Home
Construction efforts have been focused on drop installation. We are anticipating having drop install wrapped up by the end of March. Splicing and other construction activities are also expected to wrap up around the same time leaving service activation and restoration work to be completed.
Project Category | % Complete |
Conduit Installation | 99% |
Cable Placement | 91% |
Splicing | 50% |
Drop Installation | 67% |
Service Activation | 25% |
Video Service
Weekly meetings have been scheduled with CSI Digital to help move along the launch of the Yondoo video service.
Sling TV has launched their new internet TV product. It seems to be very polished and functions beautifully on the fiber network. It will likely be a great fit for many of the SandyNet Fiber customers.