Monthly Report – March 2015

Fiber to the Home

Construction efforts are nearing completion on facilities installation. Crews will be focusing on restoration activities for the next several weeks to get our beautiful city back in tip-top shape after the construction activities.

Project Category % Complete
Conduit Installation 100%
Cable Placement 100%
Splicing 80%
Drop Installation 95%
Service Activation 42%

Video Service

We are continuing testing of service with Yondoo and working with their staff to coordinate installation efforts. I expect they will be launching video service in Sandy in May or June.