Public Works – Monthly Report – June 2024

WATER:

·     Alder Creek had a Peak Day production of 1.091 MG on June 7, 2024

 ·    Alder Creek water plant production net of backwash water used was 19.869 MG

 ·    Brownell Springs production was a total of 10.76 MG and Peak Day production was on June 3rd with a total of 413,205 gallons.

 ·    Portland Water Bureau source production was a total of 6.66 MG’s with a Peak Day production of 453,739 gallons on June 5th.

 ·    We recorded a total of 4.58 inches of rainfall at the water plant with peak rainfall on June 2nd with a total of 2.44 inches.

EQUIPMENT ISSUES:

6/19/24 – Blower 3 failed, electrician was able to adjust ECM to bring it back online.

WASTEWATER:

  • Gallons of sludge pressed: .87 MG
  • On June 3rd the Peak day flow was 2.18 MG.
  • 1.27 inches of rainfall was recorded the day of and 0.26 inches the day after.
  • Monthly rainfall recorded at the plant was 2.53 inches with a peak of 1.27 inches on June 3rd.
  • Monthly Average Effluent- BOD: 1389 lbs/day & TSS: 854 lbs/day

EQUIPMENT ISSUES:

6/13 – Geamotor replaced for Tertiary filter 1
6/15 – Effluent pipe break, all flow diverted to EQ Basin
6/26 – Pipe break repaired.

·